Question # 1

The project sponsor is inappropriately requesting status reports from individual team members. The project manager plans to meet with the sponsor to discuss the issue To what should the project manager refer prior to the meeting?

A. Communications management plan
B. Risk management plan
C. Project charter
D. Work performance reports

Answer: A


Question # 2

Two team managers argue about who will perform and report the status of a particular task. What source may be consulted to help resolve this?

A. Work breakdown structure (WBS)
B. Team members' functional managers
C. Responsible, accountable, consult, and inform (RACI) matrix
D. Project sponsor

Answer: C


Question # 3

After preparing the final project report, the project manager realizes that the stakeholder distribution list is incomplete. What should the project manager do?

A. Refer to the communications management plan
B. Refer to the stakeholder list created during the development of the project charter
C. Gather inputs from the team to develop the list of stakeholders.
D. Ask the project sponsors for a list of stakeholders

Answer: A


Question # 4

A new project stakeholder is identified who has interest in, but little authority or influence on, the project.
How should the project manager handle this stakeholder?

A. Provide information to the stakeholder as needed.
B. Work closely with the stakeholder to proactively address their concerns.
C. Keep track of the stakeholder and respond to their needs.
D. Include the stakeholder on standard updates and keep them satisfied.

Answer: C


Question # 5

A project manager realizes that an issue that occurred several weeks ago has negatively impacting the schedule. When the mitigation plan is initiated, it fails because the required resources are now unavailable. 
What should the project manager have done to avoid this?

A. Updated the resource management plan
B. Sent out status reports to stakeholders
C. Conducted stand-up meetings to communicate project status
D. Reviewed and updated the risk mitigation plan

Answer: A


"For More Information - Click The Link Below"

4 comments:

  1. It would always be my priority to download study material from RealDumpsCollection. In this IT attempt I chose PMP dumps and got passed by the first attempt. My experience was positive and I learned a lot about IT. I will recommend PMP dumps to all the IT students.

    ReplyDelete
  2. You will find the CRT-450 Questions & Answers very helpful in helping you understand and study the SalesforceCRT-450 Test. Learn the CRT-450 questions and answers to pass the SalesforceCRT-450 exam. The CRT-450 questions have similar answers to the ones in the exams. Braindumps PDF

    ReplyDelete
  3. Microsoft also guarantees your success by providing highly effective content to help you pass the DP-203 Screening Exams. You will save time and have reliable, easy-to-follow content to help you succeed. Your success is up to you. We will refund you if you fail the Microsoft DP-203 Test for any reason. There is no need to worry about DP-203 study materials. Exam Dumps PDF

    ReplyDelete
  4. SAP codes has become more important every day. C_HANATEC_16 dumps pdf are essential for the success of the SAP codes C_HANATEC_16 exam dumps . We are responsible for providing reliable and easy content to ensure success. It is easy to get C_HANATEC_16 dumps and you will succeed. You can easily get C_HANATEC_16 dumps if the SAP codes C_HANATEC_16 exam changes its plan. You will receive the updated material. You can have these updates for up to three months from the date you make your selection.
    C_HANATEC_16 Dumps Questions PDF 2021

    ReplyDelete